- Investor: AMI Energy Khanh Hoa Joint Stock Company
- Implementation period: 8/2018 – 5/2019

Scope of supply:
- 110kV transformer
- 110kV/22kV primary equipment
- Measuring and protecting control cabinet
- Telecommunication and SCADA system
- Building stations and 110kV lines
- Consulting design, installation, testing commissioning and energizing to put the project into commercial operation