Starting construction for project of 220kV Ninh Hoa (Van Ninh) substation and connection line

On December 29, 2023, “Construction Deployment Ceremony of project: 220kW Ninh Hoa (Van Ninh) Substation and Connection Line” was held in Suoi Hang village, Van Khanh commune, Van Ninh district, Khanh Hoa province.

Delegates performed the project construction implementation ceremony

The project is invested by the National Power Transmission Corporation (EVNNPT), project management and administration by NPTPMB, design and supervision consultancy by Power Construction Consulting Joint Stock Company 4. Viet Technology Company Limited is the construction contractor responsible for building the 220kV substation and connecting the 220kV line.

The project has the scale of installing 01 220/110/22kV – 250 MVA transformer. The connection line section includes construction of the 220kV line connecting to the 220kV Ninh Hoa (Van Ninh) substation has a route length of 250m with a scale of 04 circuits, with the starting point connecting to the existing 220kV Tuy Hoa – Nha Trang line and the ending point is the 220kV column of 220kV Ninh Hoa (Van Ninh) substation.

The units participating in the project are determined to complete the project to meet the scheduled progress

The project’s goal is to meet the demand for power supply for regional loads, ensuring operation of 110kV substations in the northern region of Khanh Hoa province and southern Phu Yen province, especially supplying power for the load at Van Phong economic zone, ensuring stable electricity supply, meeting the socio-economic development needs of Khanh Hoa province.

Speaking at the ceremony, Deputy Director of NPTPMB – Nguyen Quang Anh said: This is an important project to ensure electricity supply for Khanh Hoa province and neighboring provinces. Therefore, NPTPMB requires units participating in the project to strictly comply with technical and regulatory procedures during the construction process; Good management of labor safety, hygiene and environment; ensure the quality of construction works.

NPTPMB requests construction units and supervision consulting units to strengthen and mobilize forces, closely coordinate with the Project Management Board and related units to ensure quality and meet the project schedule according to direction of EVNNPT.

Speaking at the ceremony, Mr. Nguyen Huu Danh – Chairman of Van Khanh Commune People’s Committee highly appreciated the role that NPTPMB has played closely in recent times with the local government so that the entire political system in the commune and district can take drastic action. Currently, the project site has been basically completed and handed over to the investor. Chairman of Van Khanh Commune People’s Committee hopes that in the coming time, NPTPMB will continue to pay attention to the commune’s social security activities, focus on environmental work, and focus resources to ensure project progress.

Mr. Tran The Tai – Representative of the construction contractor VTECH

Speaking at the ceremony, Mr. Tran The Tai – Representative of VTECH – the construction contractor committed to allocating appropriate resources, ensuring safety, quality and schedule, meeting the main objectives set out by the investor.