Connecting to power grid generating electricity from Nam San 3A Hydropower Plant and Nam San 3B Hydropower Plant from Laos to Vietnam
Viet Technology Company Limited (V.TECH) cooperates with Nam San 3A Hydropower Plant and Nam San 3B Hydropower Plant to organize training, operating instructions, acceptance of AGC system, and testing to perform COD for the two plants.
Connecting to power grid generating electricity from Nam San 3B Hydropower Plant to Vietnam
Connecting to power grid generating electricity from Nam San 3A Hydropower Plant to Vietnam
Training and instruction for operation of the Plants.
On May 29, 2023, completed testing of AGC system at Nam San 3B Hydropower Plant for all 03 units.
On May 31, 2023, completed testing of AGC system for 02 units of Nam San 3A Hydropower Plant.
Acceptance of AGC system with National Load Dispatch Center at unit 2 of Nam San 3B Hydropower Plant
During the construction process, V.TECH, as the general contractor of the project, has mobilized maximum human resources, machinery and equipment to promote and ensure the completion schedule of work items including design, supply of materials and equipment, plant renovation and COD service.
Successfully tested the AGC system for unit 1 at Nam San 3A Plant.
On June 6, 2023, EVNEPTC accepted the Commercial Operation Date (COD) for unit H2 of Nam San 3A Hydropower Plant started from 5:00 p.m. on June 5, 2023 (after the tests for the unit completed).
For unit H1 of Nam San 3A Hydropower Plant and other units of Nam San 3B Hydropower Plant, COD work is still in progress and expected to be completed in June 2023.