AMI Khanh Hoa Solar Power Plant

  • Investor: AMI Energy Khanh Hoa Joint Stock Company
  • Implementation period: 8/2018 – 5/2019
Nhà máy điện mặt trời AMI Khánh Hòa

Scope of supply:

  • 110kV transformer
  • 110kV/22kV primary equipment
  • Measuring and protecting control cabinet
  • Telecommunication and SCADA system
  • Building stations and 110kV lines
  • Consulting design, installation, testing commissioning and energizing to put the project into commercial operation